The first of the two precast concrete stair and lift cores have now been completed and work is well under way on the second of the precast cast stair cores which will form the main stairway to the upper floors of the UTC building.
A large 200 Ton crane has been set up on site to lift the larger sections that form the second stair core. The next stage will see structural steel plates being welded to the pre-fitted components within the concrete sections, which create the final connection points for the eagerly awaited steel frame. This phase of work will be completed by the middle of next week enabling the structural steel frame to then be erected.