Construction of the sub-structure for the steel framed building is now well underway. Over 100 CFA piles have been bored and 12 pile caps are ready for the delivery and erection of the steel.
During week 9 the shuttering to the fairface concrete retaining wall along the east elevation has been struck and hardcore has been laid along the wall to create a lay by area for the articulated lorries. However, this week we have concentrated on the foundation reinforcement, placing of the formwork for the future prefabricated stair and lift core.