The favourable weather conditions during week 10 have enabled the project to progress significantly. The shuttering to one of the main foundations which was poured last week has now been removed and a further 6 foundations with adjoining ground beams have been excavated, shuttered and reinforced with steel bar. This has meant that over 180 m3 of concrete have been poured over the last 5 days.
The retaining wall along Dallam Lane has also received waterproofing treatment and a worker’s site access tunnel has been erected in order to separate pedestrians and vehicles on site.