The 150 tonne crane and the first of the precast concrete stair cores, stairs and lift shaft sections arrived on site early Monday morning as expected. However, the first of this seasons storms named ‘Abigail’ has delayed some of the lifts due to the wind speeds.
Wednesday and Thursday’s improved weather conditions allowed our lifting operations to commence and by Thursday afternoon 3 stair core sections, 2 shaft lift sections and 2 flights of concrete stairs had been erected.